MedFlux
March Tethys Cruise Plan |
| |
|
|
|
| Time |
03-Mar-03 |
04-Mar-03 |
05-Mar-03 |
| |
Nice |
at
sea |
at
sea |
| |
|
|
|
| 06:00 |
|
leave
Nice |
loading
of CTD-Rosette and Engineer |
| 07:00 |
|
|
leave
Nice |
| 08:00 |
reception
of UW boxes |
|
|
| 09:00 |
anchor
delivery |
arrival
at mooring station |
|
| 10:00 |
loading
of MEL material |
*start
mooring deployment |
|
| 11:00 |
|
|
arrival
at mooring station |
| 12:00 |
|
|
*start
third in-situ pump cast |
| 13:00 |
|
*end
mooring deployment |
(lower
four depths) |
| 14:00 |
all
day at the port for preparation |
*start
first in-situ pump cast |
*end
third in-situ pump cast |
| 15:00 |
and
assembling of the mooring |
(upper
four depths) |
*CTD-Rosette
and water column sampling |
| 16:00 |
|
*end
first in-situ pump cast |
|
| 17:00 |
|
(pumps
recharging) |
|
| 18:00 |
|
*test
large net trap |
|
| 19:00 |
|
*start
second in-situ pump cast |
*end
water column work |
| 20:00 |
|
(middle
four depths) |
return
to Nice |
| 21:00 |
|
*end
second in-situ pump cast |
|
| 22:00 |
|
return
to Nice |
|
| 23:00 |
|
(pumps
recharging) |
|
| 00:00 |
|
|
|
| 01:00 |
|
arrival
to Nice |
arrival
to Nice |
| 02:00 |
|
|
|
| |
-
The third pump cast can eventually be done at the end of the second
day |
| |
before returning to Nice
to pick-up the CTD and the Engineer |
| |
-
If time sufficient another pump cast can be considered |